Progress Continues on Fiber Expansion Projects
June 10, 2022
Twin Valley is bringing high-speed internet up to 2 Gbps symmetrical to rural Kansans with a mix of fiber to the premises and next-gen fixed wireless.
Learn About Our Fiber ProjectsJune 10, 2022
A little rain (ok, a lot) isn’t going to get us down! Despite the high amounts of rainfall this spring, we have continued to march forward with expanding our fiber broadband network in rural Haysville, Clearwater, and Viola. These projects reflect our commitment to improving connectivity to rural Kansans, providing the most reliable network with internet options at the best value.
With these projects, we are rolling out new symmetrical internet speeds – equal download and upload speeds – up to 1 Gbps or 1,000 Mbps. That’s more than 50 times faster download and a thousand times faster upload than currently available. Faster download creates a better experience for all your online activities, including streaming TV, gaming, working from home, taking online classes, and more. Activities such as gaming, working from home, and uploading large files require faster upload speeds. Check out the current status of our 2022 fiber expansion projects and watch for news on upcoming project announcements.
Homes and Businesses Served: 25
Status: Completed in May
Grant Funding: Made possible in part thanks to a Broadband Acceleration Grant awarded by the State of Kansas.
Homes & Businesses Served: 17
Status: Completed in April
Homes & Businesses Served: 17
Status: Construction and fiber splicing is complete. Installations begin in June.
Anticipated Completion: June 2022
Homes & Businesses Served: 44
Status: Our construction partner, DLS Underground, will place the mainline duct and pull in the fiber-optic cable in June. Next, crews will begin burying fiber to homes, complete splicing, and begin installations.
Anticipated Completion: July 2022
Homes & Businesses Served: 17
Status: Construction will begin soon.
Anticipated Completion: Late summer or early fall
Homes & Businesses Served: 21
Status: Our partner, Wichita Utilities, is nearing completion on construction, including mainline and drops to homes. Next, crews will complete splicing and begin installations.
Anticipated Completion: Late summer or early fall